Field · Work orders
Work order cost
Every work order knows what it cost. The cost is the sum of three parts: participants' labour at the hourly rate from the moment they were assigned, machines at their own rate for the order's duration, and materials at the store's weighted average cost. Pauses do not count towards duration. Spraying parcel P2 took 3.5 hours and cost 17,630 RSD.
Two workers at 450 RSD/h work 3.5 h: labour costs 3,150 RSD.
Tractor T-04 runs 3.5 h at 2,800 RSD/h: the machine costs 9,800 RSD.
1.2 l of product at a weighted average cost of 3,900 RSD/l: materials cost 4,680 RSD.
The order adds up all three parts: spraying parcel P2 cost 17,630 RSD.
How the cost builds up
Participants with rates
Workers, users or a whole team go on the order. Each keeps the hourly rate from the moment of assignment, so a later raise does not change past orders.
Machines
Every machine on the order carries its own rate. Machine cost is that rate times the order's duration.
Materials
Product, fertiliser or packaging is added with the store it comes from and valued at that store's weighted average cost.
Completion
Duration is the time In progress, without pauses. Participants with no hours entered get the order's duration, and the cost stays on the order.
What the work order cost adds up
Cost
- A work order's cost is the sum of participants' labour, machine hours and materials used.
- Each participant keeps the hourly rate from the moment they were assigned, so a later rate change does not alter past orders.
- Materials on a work order are valued at the weighted average cost of the store they come from.
- A work order's duration is the total time spent In progress; pauses do not count.
- When a work order is completed, participants with no hours entered get the order's duration and their labour is costed automatically.
The same in other parts of the field
Growers' questions
Can a worker have a different rate on one order?
Yes. A participant's rate is changed on the order itself while it is not completed, and only by a user with that permission.
What if two machines work on the order?
Each is costed at its own rate. A tractor and a sprayer on the same order give two cost lines for the same duration.
How is a team order costed?
The team is added at once: the team leader and every member become participants, each with their own rate, and a member with a special rate in the team gets that rate.
Show us your harvest
In one call we walk your path from the row to the truck and show it in the system, with your varieties and parcels.